At
Berneche2 Architecture we do both residential and commercial project types.
Most of our project are single-family residences (houses) but for the
past two years we have been working with Queen of All Saints Parish in Michigan
City, Indiana to develop a new Parish Center. On Tuesday October 27, 2015
I presented the project to DuPage Referral Network to show an example of our
non-residential work.
The initial call was that they
wanted to add "a meeting room". We visited Father Kevin and he
showed us a modular classroom building that needed several repairs, and the
thought was it would be more practical to do an addition versus spending
$50,000 to repair a temporary structure. So a meeting room became four
classrooms, though these would now be used by church groups so Meeting Rooms
was the appropriate term.
Next the thought was that a
meditation chapel created in a 1999 addition was not very conducive to
meditation because the school library was upstairs. So it was decided to
move that into the addition.
Finally, the existing 1965 church
was designed with an undersized Narthex. A Narthex is an entry space akin
to a theater lobby, where people can meet and have fellowship before and after
a service. The Narthex for the church was more of an eleven-foot wide
corridor that is not very conducive to groups.
The project has several goals:
1. The new facility will connect
together a 1950 split-level school building and a 1965 church, which are 70
feet apart. The addition main floor level will match the church.
2. An elevator is required for
accessibility. The Americans with Disabilities Act exempts religious
facilities from the need to comply as they are considered private entities.
However, other codes adopted by the state do consider churches as public
facilities and therefore must comply. It will be a two-sided elevator
situated against the school and the school floor levels will extend into the
elevator lobby to make the school wheelchair accessible.
3. A two-story facility was
eventually agreed upon. The design went through two major versions.
In the first the gathering space was broken up into two parts, a large
glass atrium off the main parking lot, and then a carped seating area closer to
the church. The chapel, meeting rooms, and toilet rooms were placed
adjacent to the church for structural reasons. The church committee felt
strongly that the gathering space should be located right outside the church.
Concepts were developed to make this happen. Both one and two story
options were presented, the latter with intent to save cost. While the
two-story concept will cost a little more, it will take up less of the site and
fewer parking spaces and outdoor areas will be lost.
4. Building codes allow churches
to have minimal toilet facilities, likely anticipating that most folks are
there for an hour and then leave. For the 700-seat church there is a
single men's and women's toilet. This is inadequate for the current after
hours uses, and will not be sufficient for groups meeting here. The new
facility will have two groups of toilet rooms, one on each level, and 16 new
toilets/urinals will be available.
5. The four meeting rooms were
designed to work as six rooms, two rooms divided into smaller rooms, as the
size of the original rooms is much larger than required by most groups.
There will be two groups of rooms, one on each level, and each will be
divided with operable partitions which can be opened to allow all three rooms
to become one large meeting room when needed.
6. Father Kevin truly wanted to
have the glass doors between the gathering space and church to visually connect
the spaces. Originally we had these as solid doors with small windows in
a three-hour fire wall to separate the two buildings. However, this
became important enough to where we will be adding a sprinkler system to the
church, allowing us to eliminate the fire wall and use full glass doors.
We still need to maintain a two-hour fire wall between the school
building and addition, and security of the school warrants the separation
anyway.
7. One major issue being
addressed are the site utilities. When the building was constructed
galvanized pipe was used for the school water supply. The City is
requiring a backflow preventer on this line as well. There were also some
utilities between buildings not documented on older drawings and some of these
will have to be relocated. The Civil engineer notified us that there is a
major
We first met with Father Kevin
June 2013 to initially discuss the project. With the initial concept we
worked with their fundraising team to communicate the intent to the
parishioners, which included hiring a 3d rendering company to develop a fly
over animation of the project. We were authorized to commence
construction documents Spring 2015, and we are currently completing drawings
and specifications to be released to bidders December 2015. Construction
is scheduled to begin June 2016 after the Parish Festival. The
construction phase is anticipated to last nine months.
It has been exhilarating,
challenging, and very rewarding working on a larger project again. I
worked at a K-12 school planning firm 1995-2004 and it has been wonderful to
work on a project of this scale with our own firm. We look forward to
doing many more.
Images of the progress can be
seen on our Berneche2 Architecture Facebook Page.
Tim Berneche
No comments:
Post a Comment